Contractor Representatives
Call 3-1-1 to report construction related issues
Ms. Jody Craze
Sr. Project Manager
City of Houston
This email address is being protected from spambots. You need JavaScript enabled to view it.
Phone; 832-395-2392
Fax: 832-395-2403
Total Contracting Limited
Project Manager: Moises Ayala 832-262-0221 (c)
Project Superintendent: Luke Morganti 832-265-7470 (c)
Superintendent: Jose Diaz 832-265-7434 (c)
Schedule
From February 19, 2013 to July 2013
Reconstruction of Bellaire Blvd eastbound lanes and installation of some segments of proposed underground utilities (storm water, water distribution lines and wastewater collection lines) will be completed.
From August 2013 to December 2013
Reconstruction of Bellaire Blvd westbound lanes, including the addition of the 4th westbound lane and installation of remaining segments of proposed underground utilities (storm water, water distribution lines and wastewater collection lines) will be completed.
From February 11, 2014 to September 2014
Installation of hardscaping elements, landscaping elements and other miscellaneous items throughout the project limits will be completed.
September 2014
End Project Construction
Project Presentation
Field Project Office
7001 Corporate Dr, Suite 211
Houston, TX 77036
Email Updates
About the Project
English | Spanish | Vietnamese | Chinese
LIMITS: FROM ROGERDALE RD TO OSAGE ST
WBS No. N-T02001-0001-4
Project Description
The Bellaire Boulevard Reconstruction Project is a joint project between the Southwest Houston Redevelopment Authority (SHRA) and the City of Houston (COH). The SHRA was responsible for the design of the project. The COH will be responsible for the construction of the project. The project will consist of several types of improvements along the Bellaire Boulevard corridor from Rogerdale Road to Osage Road. Below is a summary of the different types of improvements and upgrades that will be constructed with this project:
Project Components
Roadway Improvements
- Rebuild the roadway
- Dedicated left turn lanes
- Addition of one westbound lane to the roadway
- Dedicated turn lanes at Beltway 8 frontage roads
Underground Utility Improvements
- Install new storm sewer system to increase the Existing Storm Sewer System
- Replace Existing Water Lines and services
- Replace Existing Wastewater Lines and services
Hardscape and Landscape Improvements
- Replace old sidewalks with new concrete sidewalks with paver insets
- Pavers
- Benches
- Over 250 Trees Planted
- Traffic Signal Planter Rings
- Planter Walls
- Irrigation Systems
- Planter Pots
- Street Lights
Traffic Management Improvements
- Install new Traffic Signals with Pedestrian communications
- Beltway 8 northbound and southbound frontage roads
- Pella Dr.
- Corporate Dr.
- Ranchester Dr.
- Gessner Rd.
- Mary Bates Blvd
- Harbor Town Dr.
- Special Street Signs for SHRA/GSMD
Construction Costs
WATER AND SEWER = $4.2 M
DRAINAGE = $3.1 M
ROADWAY = $5.7 M
LANDSCAPE/HARDSCAPE = $2.4 M
OTHER GENERAL ITEMS = $6.5 M
- (Removal of structures, Traffic/Ped Signals, HCTRA Fiber)
TOTAL CONSTRUCTION COSTS = $21.9 M
CONST. MGMT AND OTHER COSTS = $3.1 M
TOTAL ALL PROJECT COSTS = $ 25.0 M
Sequence of Construction (730 calendar days)
- Private Utility Relocations (Almost Complete)
- Temporary Roadway
- Underground Utilities
- Paving and Traffic Signals
- Landscape and Hardscape
- Restoration and Cleanup
Project Estimated Construction Schedule
- September 2012 => Begin Project Construction
- From September 2012 to December 2012 => Improvements to Beltway 8 frontage roads and construction of temporary asphalt pavement in the current median (for future use) will be completed.
- From February 19, 2013 to July 2013 => Reconstruction of Bellaire Blvd eastbound lanes and installation of some segments of proposed underground utilities (storm water, water distribution lines and wastewater collection lines) will be completed.
- From August 2013 to December 2013 => Reconstruction of Bellaire Blvd westbound lanes, including the addition of the 4th westbound lane and installation of remaining segments of proposed underground utilities (storm water, water distribution lines and wastewater collection lines) will be completed.
- From February 11, 2014 to September 2014 => Installation of hardscaping elements, landscaping elements and other miscellaneous items throughout the project limits will be completed.
- September 2014 => End Project Construction
Note: Contractor is required to shut down construction activities on the project for December Holidays through Chinese New Year on the following dates: December 15, 2012 to February 18, 2013 and December 14, 2013 to February 10, 2014
During this period, the Contractor is required to
- Open all lanes of traffic with temporary pavement
- Open all sidewalks
- Place temporary traffic signals where required
- Remove all traffic control devices, equipment and materials
- Clean up the area
Access During Construction
- Major intersection access are maintained at all times with reduced lanes and temporary traffic signals
- Alternate side streets will be closed with detours to the next nearest side street access
- Driveway access to be maintained at all times if possible. Any driveway closures for construction will be coordinated with the property owner a minimum of 7 days prior to closure.
- Use of off-duty peace officers and certified flaggers, especially at schools
Project Construction Contact Information
For routine/non-emergency issues, the public is urged to contact the City of Houston using the following options:
- Houston 311 hotline (Dial 311 for City's non-emerigency department directory and self-service city request line)
- Houston 311 website (http://hfdapp.houstontx.gov/311/index.php)
City Council District Members - City of Houston
| City Council District F: | Al Hoang | 832-393-3002 (o) |
| City Council District J: | Mike Laster | 832-393-3015 (o) |
Contractor Representatives - Total Contracting Limited
| Project Manager: | Moises Ayala | 832-262-0221 (c) |
| Project Superintendent: | Luke Morganti | 832-265-7470 (c) |
| Superintendent: | Jose Diaz | 832-265-7434 (c) |
| Community Liaison: | Yuzhen Liang | 832-955-8608 (c) |
City Representatives - City of Houston
| Project Manager: | Jody Craze | 832-395-2392 (o) |
| Senior Inspector: | Mike Beezley | 281-217-3446 (c) |
| Inspector: | Jerry Morgan | 713-876-6315 (c) |
| Inspector: | Art Becker | 713-562-3942 (c) |

